Bid Result

Rehabilitation of the HLCT Manhattan Plaza

AgencyMTA Construction & Development
SolicitationHC-48
TradeConstruction
Bids openedJune 25, 2025
Bidders10
Apparent lowJ-TRACK LLC — $38,337,094
Spread0.3% (second-low vs. low)
First listedSeptember 3, 2026
RecordRFI-001911

Bids opened June 25, 2025. 10 bidders. A+B contract — bidders bid price and schedule together. Apparent low on the combined math: J-TRACK LLC at $38,337,095 evaluated ($32,010,095 price before the schedule value). Bids are under review — not yet an award.

BidderBid
J-TRACK LLC$38,337,094
C A C INDUSTRIES INC.$38,439,000
JUDLAU CONTRACTING, INC.$41,098,140
RESTANI CONSTRUCTION CORP$41,698,443
BOVE INDUSTRIES INC$42,831,000
POSILLICO CIVIL INC$42,844,569
PAUL J. SCARIANO, INC.$44,911,000
TULLY CONSTRUCTION CO., INC.$45,201,100
NAVILLUS CONTRACTING INC$46,084,280
FOS DEVELOPMENT CORP$46,753,485

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.