The RFI Wire

HomeThe RFP Wire › RFI-001896

Bid Result

Traffic Control Devices and Warning Signage Queens Midtown Tunnel and Hugh L. Carey Tunnel

AgencyMTA Construction & Development
SolicitationAW-80C
TradeConstruction
Bids openedJuly 14, 2026
Bidders4
Apparent lowHELLMAN ELECTRIC LLC — $20,989,300
Spread2.9% (second-low vs. low)
First listedSeptember 3, 2026
RecordRFI-001896

Bids opened July 14, 2026. 4 bidders. Apparent low: HELLMAN ELECTRIC LLC at $20,989,300. Bids are under review — not yet an award.

BidderBid
HELLMAN ELECTRIC LLC$20,989,300
E.J. ELECTRIC INSTALLATION CO.$21,590,000
CRC ASSOCIATES, INC$23,119,400
TC ELECTRIC, LLC$25,062,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

MTA C&D — Bid Results → The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication