Home › The RFP Wire › RFI-001247
Bid Result
| Bids opened | January 13, 2025 |
| Bidders | 6 |
| Apparent low | Honey Construction NY, Inc — $1,159,683 |
| Spread | 123.8% (second-low vs. low) |
| Record | RFI-001247 |
Apparent low bidder: Honey Construction NY, Inc at $1,159,683 - from bid-opening records, subject to verification and not yet a confirmed award. 6 bids received.
| Bidder | Bid |
|---|---|
| Honey Construction NY, Inc | $1,159,683 |
| MDS Construction Management, Llc | $2,595,016 |
| Mac Contractor Inc | $2,794,000 |
| Sky Heights Construction Corp. | $2,897,860 |
| Arora Construction Inc. | $2,983,000 |
| N.B.A Construction Inc | $3,900,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication