Upgrade Domestic Hot Water System, Building 83 at Pilgrim Psychiatric Center - HVAC Work

AgencyNYS Office of Mental Health
Bids openedJanuary 22, 2025
Bidders5
Apparent lowUltimate Power, Inc. — $902,160
Spread26.6% (second-low vs. low)
RecordRFI-001239

Apparent low bidder: Ultimate Power, Inc. at $902,160 - from bid-opening records, subject to verification and not yet a confirmed award. 5 bids received.

BidderBid
Ultimate Power, Inc.$902,160
Premier Mechanical Services Inc$1,141,860
ACS System Associates, Inc.$1,209,160
Rocon Plumbing and Heating Corp.$1,394,000
ANR Mechanical Corp.$1,627,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.