| Bids opened | May 13, 2025 |
| Bidders | 26 |
| Apparent low | Singh Landscaping & Lawn Sprinkler Corp. — $2,559,051 |
| Spread | 12.4% (second-low vs. low) |
| Record | RFI-001132 |
Apparent low bidder: Singh Landscaping & Lawn Sprinkler Corp. at $2,559,051 - from bid-opening records, subject to verification and not yet a confirmed award. 26 bids received.
| Bidder | Bid |
|---|---|
| Singh Landscaping & Lawn Sprinkler Corp. | $2,559,051 |
| Elite Renovation & Builders Corp. | $2,876,000 |
| Bagiana Construction Inc | $2,933,919 |
| Nikhi Contracting Corp | $2,970,000 |
| Spencer Contracting LLC | $2,973,750 |
| CM&E CON, Inc. | $3,021,000 |
| Jaysan Contracting Corp | $3,275,188 |
| Pro Con Group Inc. | $3,292,000 |
| Verdugos General Contractors Corp | $3,333,217 |
| Fidelis Contracting Inc. | $3,367,000 |
| Perfetto Enterprises Company Inc. | $3,773,000 |
| Skyview Construction Company | $3,814,000 |
| Gem Quality Corp. | $3,836,430 |
| IBEX Contracting Inc. | $3,939,892 |
| Amcon Contracting Corp. | $3,988,000 |
| Capital Projects Inc. | $3,992,760 |
| National Environmental Safety Company, Inc. | $4,122,000 |
| AKM Construction Services Corp. | $4,150,000 |
| Red & Blue Construction Corp | $4,237,700 |
| Venus Group, Inc. | $4,259,000 |
| MDS Construction Management, Llc | $4,444,016 |
| Olympic Contracting Corp. | $4,649,000 |
| CVM Construction Corp | $4,994,000 |
| Kel-Tech Construction, Inc | $6,800,000 |
| Maven Construction Corp. | $7,689,000 |
| Litehouse Builders, Inc. | $9,388,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication