Bid Result
| Bids opened | May 20, 2025 |
| Bidders | 20 |
| Apparent low | Maven Construction Corp. — $12,904,000 |
| Spread | 7.8% (second-low vs. low) |
| Record | RFI-001121 |
Apparent low bidder: Maven Construction Corp. at $12,904,000 - from bid-opening records, subject to verification and not yet a confirmed award. 20 bids received.
| Bidder | Bid |
|---|---|
| Maven Construction Corp. | $12,904,000 |
| Zaman Construction Corp. | $13,913,168 |
| KOKO Contracting, Inc. | $14,560,000 |
| Amcon Contracting Corp. | $14,588,000 |
| Northeast Restoration Corp | $14,842,000 |
| Whitestone Construction Corp. | $14,891,000 |
| Imperium Construction, Inc. | $14,941,000 |
| Allcon Contracting Corp | $14,941,000 |
| Venus Group, Inc. | $14,953,000 |
| Kel-Tech Construction, Inc | $15,100,000 |
| Ashnu International, Inc | $15,113,919 |
| ABC Construction Contracting, Inc. | $15,430,000 |
| Gem Quality Corp. | $15,574,299 |
| PMY Construction Corp. | $16,226,199 |
| P&K Contracting Inc. | $16,250,000 |
| CVM Construction Corp | $16,400,000 |
| Adam's European Contracting, Inc | $16,909,000 |
| T.A. Ahern Contractors Corp dba Ahern Painting | $16,927,272 |
| Skyline Industries LLC | $18,368,000 |
| Litehouse Builders, Inc. | $18,688,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List