Bid Result
| Bids opened | May 20, 2025 |
| Bidders | 5 |
| Apparent low | Stalco Construction, Inc. — $724,000 |
| Spread | 15.3% (second-low vs. low) |
| Record | RFI-001119 |
Apparent low bidder: Stalco Construction, Inc. at $724,000 - from bid-opening records, subject to verification and not yet a confirmed award. 5 bids received.
| Bidder | Bid |
|---|---|
| Stalco Construction, Inc. | $724,000 |
| Crossroads Construction Corp | $835,000 |
| Preferred Construction Inc. | $1,116,000 |
| JMF Contracting Inc. | $1,574,000 |
| Irwin Contracting Inc. | $1,784,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List