Florence Nightingale PS 110 (M) Facade Remediation, Roofs, Parapets, Flood Elimination - Rebid

Bids openedMay 22, 2025
Bidders13
Apparent lowArmy Construction, Llc — $12,326,200
Spread5.4% (second-low vs. low)
RecordRFI-001107

Apparent low bidder: Army Construction, Llc at $12,326,200 - from bid-opening records, subject to verification and not yet a confirmed award. 13 bids received.

BidderBid
Army Construction, Llc$12,326,200
B N Restoration Inc.$12,997,786
Spencer Contracting LLC$15,897,500
Universal Construction Resources, Inc.$16,270,000
Adam's European Contracting, Inc$16,299,000
RSN Construction Co, Inc.$16,384,000
Alliance Tri-State Construction, Inc.$17,365,000
Kel-Tech Construction, Inc$17,900,000
Maven Construction Corp.$18,362,000
CVM Construction Corp$18,649,000
Pro-Metal Construction, Inc$18,824,000
KOKO Contracting, Inc.$19,550,000
Litehouse Builders, Inc.$19,888,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication