Bid Result

PS 198 (K) FY24 Reso A (MA) Cafeteria Upgrade, Path of Travel

Bids openedMay 27, 2025
Bidders9
Apparent lowWorldnet Construction — $701,000
Spread1.4% (second-low vs. low)
RecordRFI-001102

Apparent low bidder: Worldnet Construction at $701,000 - from bid-opening records, subject to verification and not yet a confirmed award. 9 bids received.

BidderBid
Worldnet Construction$701,000
Brikmor, Inc.$710,994
Archinova Builders LLC$723,954
BCR Construction Corporation$760,000
JPR Builders 07 Inc.$795,000
On Top Renovation Inc.$797,127
Where To Get It Services, LLC$805,000
Shining Sky Inc.$819,000
Bullay Shah Inc$846,638

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.