Bid Result

City University of New York Queens College Exterior ADA Upgrades and Hazmat Abatement

AgencyCUNY
Bids openedMay 28, 2025
Bidders15
Apparent lowZHN Contracting Corp — $3,731,398
Spread5.7% (second-low vs. low)
RecordRFI-001091

Apparent low bidder: ZHN Contracting Corp at $3,731,398 - from bid-opening records, subject to verification and not yet a confirmed award. 15 bids received.

BidderBid
ZHN Contracting Corp$3,731,398
Cauldwell Wingate Company, LLC$3,942,459
Pioneer Landscaping (Paving)$4,266,000
Apollon Group, LLC$4,868,234
JCC Construction Corp.$5,299,793
Gohar Construction Corp.$5,375,013
Sharan Builders Inc.$5,482,162
Medco Electric, Inc$5,750,000
JRCRUZ Corp$5,874,500
Empire Control Abatement, Inc.$5,985,000
Pb Contracting Corp.$6,490,000
JM&A Construction Corp$6,707,960
Lanmark Group, Inc$6,795,000
Fidelis Contracting Inc.$6,850,000
Fratello Construction Corp.$6,969,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.