Bid Result

PS 85/Minischool 885 (X) Non-TCU Temporary Structure Removal, Reso A Auditorium Upgrade, Playground Upgrades, Path of Travel

Bids openedJune 2, 2025
Bidders15
Apparent lowRed & Blue Construction Corp — $4,865,500
Spread5% (second-low vs. low)
RecordRFI-001076

Apparent low bidder: Red & Blue Construction Corp at $4,865,500 - from bid-opening records, subject to verification and not yet a confirmed award. 15 bids received.

BidderBid
Red & Blue Construction Corp$4,865,500
Verdugos General Contractors Corp$5,110,712
Spencer Contracting LLC$7,184,750
B & R Construction Services Corp$7,300,000
Nikhi Contracting Corp$7,491,600
National Environmental Safety Company, Inc.$7,844,000
Venus Group, Inc.$7,865,000
PMY Construction Corp.$8,049,600
CM&E CON, Inc.$8,521,000
Perfetto Enterprises Company Inc.$8,925,000
2 Saab Construction$9,430,000
Maven Construction Corp.$9,938,000
AKM Construction Services Corp.$11,126,200
CVM Construction Corp$13,044,000
Litehouse Builders, Inc.$18,718,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.