Home › The RFP Wire › RFI-001028
Bid Result
| Bids opened | June 11, 2025 |
| Bidders | 20 |
| Apparent low | KOKO Contracting, Inc. — $12,340,000 |
| Spread | 12.1% (second-low vs. low) |
| Record | RFI-001028 |
Apparent low bidder: KOKO Contracting, Inc. at $12,340,000 - from bid-opening records, subject to verification and not yet a confirmed award. 20 bids received.
| Bidder | Bid |
|---|---|
| KOKO Contracting, Inc. | $12,340,000 |
| Maven Construction Corp. | $13,838,000 |
| Kel-Tech Construction, Inc | $14,000,000 |
| Venus Group, Inc. | $14,497,000 |
| Corbex, Inc. | $14,800,000 |
| CVM Construction Corp | $15,333,000 |
| BQE Industries, Inc. | $15,400,000 |
| Zarco Contracting Inc. | $15,819,000 |
| Litehouse Builders, Inc. | $16,588,000 |
| Amcon Contracting Corp. | $16,750,000 |
| Imperium Construction, Inc. | $16,785,000 |
| Nehal Contracting, Inc. | $16,912,000 |
| Whitestone Construction Corp. | $17,253,000 |
| Civil Contracting Corp. | $17,868,000 |
| Zaman Construction Corp. | $17,928,665 |
| Pro-Metal Construction, Inc | $18,847,000 |
| Carnak Construction Inc. | $19,557,000 |
| Northeast Restoration Corp | $19,800,000 |
| ABC Construction Contracting, Inc. | $21,810,000 |
| ANSU Construction Inc. | $22,488,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication