The RFI Wire

HomeThe RFP Wire › RFI-001012

Bid Result

Tandem IS 129, PS 234 at PS 300 (X) TCU Removal Playground Redevelopment, Playground Upgrade, Path of Travel

Bids openedJune 12, 2025
Bidders8
Apparent lowBagiana Construction Inc — $3,656,919
Spread8.9% (second-low vs. low)
RecordRFI-001012

Apparent low bidder: Bagiana Construction Inc at $3,656,919 - from bid-opening records, subject to verification and not yet a confirmed award. 8 bids received.

BidderBid
Bagiana Construction Inc$3,656,919
Spencer Contracting LLC$3,983,750
PMY Construction Corp.$4,019,994
Dynamic Construction Company dba Ziaur Bhuiyan$4,129,975
Musa Builder Corp.$4,498,869
B & R Construction Services Corp$4,638,000
Venus Group, Inc.$4,887,000
Olympic Contracting Corp.$4,900,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication