Bid Result

CUNY Herbert H. Lehman College Campus Central Bridge and Concert Hall Entry Plaza - Rebid

AgencyCUNY
Bids openedJune 24, 2025
Bidders13
Apparent lowZHN Contracting Corp — $4,503,787
Spread9.5% (second-low vs. low)
RecordRFI-000995

Apparent low bidder: ZHN Contracting Corp at $4,503,787 - from bid-opening records, subject to verification and not yet a confirmed award. 13 bids received.

BidderBid
ZHN Contracting Corp$4,503,787
Gohar Construction Corp.$4,930,013
Pioneer Landscaping (Paving)$5,132,892
Pb Contracting Corp.$5,490,000
Fidelis Contracting Inc.$6,280,000
SRR Holdings LLC$6,533,786
B N Restoration Inc.$6,966,786
Spencer Contracting LLC$6,999,751
Constructomics LLC$7,399,000
ABCD Construction Corp$8,175,000
Padilla Construction Services, Inc$9,237,760
JRCRUZ Corp$9,276,998
Lanmark Group, Inc$10,145,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.