The RFI Wire

HomeThe RFP Wire › RFI-000983

Bid Result

CUNY Herbert H. Lehman College Carman Hall Restroom Upgrades and Asbestos Abatement - Rebid

AgencyCUNY
Bids openedJuly 10, 2025
Bidders15
Apparent lowVernon Construction & Development — $5,674,000
Spread11.7% (second-low vs. low)
RecordRFI-000983

Apparent low bidder: Vernon Construction & Development at $5,674,000 - from bid-opening records, subject to verification and not yet a confirmed award. 15 bids received.

BidderBid
Vernon Construction & Development$5,674,000
SRR Holdings LLC$6,336,786
Sienia Construction Inc$6,432,750
APN Construction Corp.$6,783,000
B N Restoration Inc.$6,797,786
Constructomics LLC$6,864,000
Stalco Construction, Inc.$6,880,000
National Environmental Safety Company, Inc.$6,888,000
Pb Contracting Corp.$6,999,991
Zaman Construction Corp.$7,374,090
Atlantic Specialty Inc$7,576,786
Jemco Electrical Contractors, Inc.$7,881,568
Lanmark Group, Inc$7,915,000
Cube Construction Services LLC$8,257,789
B&B Contracting Group$8,795,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication