The RFI Wire

HomeThe RFP Wire › RFI-000944

Bid Result

2023 Capital Bond Project Phase 1 at Hawthorne Elementary School

Bids openedSeptember 9, 2025
Bidders4
Apparent lowADP Group Inc. — $6,184,000
Spread1.8% (second-low vs. low)
RecordRFI-000944

Apparent low bidder: ADP Group Inc. at $6,184,000 - from bid-opening records, subject to verification and not yet a confirmed award. 4 bids received.

BidderBid
ADP Group Inc.$6,184,000
Pierotti Corp.$6,292,700
Piazza, Inc.$6,412,000
APS Contracting, Inc dba Asphalt Paving Systems$7,540,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication