The RFI Wire

HomeThe RFP Wire › RFI-000819

Bid Result

PS 205 (X) FY25 Reso A Cafeteria Upgrade

Bids openedJanuary 28, 2026
Bidders8
Apparent lowThe Prime LLC — $496,000
Spread2.8% (second-low vs. low)
RecordRFI-000819

Apparent low bidder: The Prime LLC at $496,000 - from bid-opening records, subject to verification and not yet a confirmed award. 8 bids received.

BidderBid
The Prime LLC$496,000
Bigger Than Buildings LLC$509,987
Pristine Construction NY LLC$513,169
Onafuwa Management Enterprise , LLC$558,967
First World Development Corporation$595,900
Afforda Inc$649,722
York Castle Construction, Inc.$718,000
B & K General Contracting Inc.$772,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication