PS 212 (Q) FY26 Reso A Multimedia Center Upgrade, Path of Travel

Bids openedFebruary 5, 2026
Bidders7
Apparent lowBrick Solution Construction Service Inc. — $554,000
Spread1.1% (second-low vs. low)
RecordRFI-000809

Apparent low bidder: Brick Solution Construction Service Inc. at $554,000 - from bid-opening records, subject to verification and not yet a confirmed award. 7 bids received.

BidderBid
Brick Solution Construction Service Inc.$554,000
NKG Corp.$560,221
Admire Construction, Inc$622,000
BCR Construction Corporation$647,000
DRL Services LLC$669,000
Sampson Laurier Williams LLC$692,000
B & K General Contracting Inc.$730,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.