Home › The RFP Wire › RFI-000758
Bid Result
| Bids opened | March 24, 2026 |
| Bidders | 8 |
| Apparent low | NORCO Construction — $2,797,056 |
| Spread | 10.4% (second-low vs. low) |
| Record | RFI-000758 |
Apparent low bidder: NORCO Construction at $2,797,056 - from bid-opening records, subject to verification and not yet a confirmed award. 8 bids received.
| Bidder | Bid |
|---|---|
| NORCO Construction | $2,797,056 |
| Renu Restoration & Contracting | $3,087,000 |
| Preferred Construction Inc. | $3,133,000 |
| Stalco Construction, Inc. | $3,360,000 |
| Irwin Contracting Inc. | $3,370,000 |
| J & H Contracting Inc | $3,472,000 |
| W.J. Northridge Construction Corp. | $3,705,000 |
| Construction Consultants LI | $4,072,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication