Bid Result
| Bids opened | March 26, 2026 |
| Bidders | 20 |
| Apparent low | New Safeway Contracting corp. — $1,111,817 |
| Spread | 121.6% (second-low vs. low) |
| Record | RFI-000755 |
Apparent low bidder: New Safeway Contracting corp. at $1,111,817 - from bid-opening records, subject to verification and not yet a confirmed award. 20 bids received.
| Bidder | Bid |
|---|---|
| New Safeway Contracting corp. | $1,111,817 |
| Bagiana Construction Inc | $2,463,919 |
| Capital Projects Inc. | $2,636,767 |
| Safecon Builders Corp. | $2,825,000 |
| Olympic Contracting Corp. | $2,947,000 |
| PMY Construction Corp. | $3,059,991 |
| Spencer Contracting LLC | $3,124,800 |
| National Environmental Safety Company, Inc. | $3,188,000 |
| Venus Group, Inc. | $3,193,000 |
| Parada General Contracting Inc | $3,194,951 |
| B N Restoration Inc. | $3,197,786 |
| Dynamic Construction Company dba Ziaur Bhuiyan | $3,351,000 |
| Fidelis Contracting Inc. | $3,383,000 |
| 2 Saab Construction | $3,400,000 |
| Nikhi Contracting Corp | $3,419,100 |
| Red & Blue Construction Corp | $3,595,100 |
| K&V Construction Inc. | $3,651,030 |
| CM&E CON, Inc. | $3,675,000 |
| Max Builders, Inc. | $3,785,000 |
| Darcon Construction, Inc. | $4,948,000 |
Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.
Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List
© The RFI Wire · A Managed Construction Publication