Bid Result

2022 Bond Related Capital Improvement Program at Manhasset Secondary School - Phase 3 - Rebid

Bids openedMay 13, 2026
Bidders6
Apparent lowJNH Construction Group Inc. — $388,000
Spread52.8% (second-low vs. low)
RecordRFI-000492

Apparent low bidder: JNH Construction Group Inc. at $388,000 - from bid-opening records, subject to verification and not yet a confirmed award. 6 bids received.

BidderBid
JNH Construction Group Inc.$388,000
Crossroads Construction Corp$593,000
Renu Restoration & Contracting$597,000
Irwin Contracting Inc.$757,700
W.J. Northridge Construction Corp.$765,740
Stalco Construction, Inc.$770,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List