The RFI Wire

HomeThe RFP Wire › RFI-000367

Bid Result

PS 195/982 (X) Non-TCU Removal-Mini Building, Other Temporary Structure Removal, Playground Redevelopment, Path of Travel

Bids openedJune 18, 2026
Bidders4
Apparent lowHoney Construction NY, Inc — $2,878,161
Spread3.3% (second-low vs. low)
RecordRFI-000367

Apparent low bidder: Honey Construction NY, Inc at $2,878,161 - from bid-opening records, subject to verification and not yet a confirmed award. 4 bids received.

BidderBid
Honey Construction NY, Inc$2,878,161
Muzi Construction Corp$2,974,000
Jaysan Contracting Corp$2,977,000
Arora Construction Inc.$4,276,000

Results as read at the public bid opening; subject to review and award. The apparent low bidder is not the awardee until the owner makes an award.

The live bid board

Always confirm dates and requirements on the issuing agency's own posting before pricing a job — dates move, and addenda are what move them. Search everything · Get The Punch List